Address:

  • Address: 2 Misr Al-Taamir Buildings, Zahraa El-Maadi St., Cairo, Egypt

Email

  • infoegypt@mencogroup.com

20227544109

  • 20227544109

Since its inception in 2008, MENCO has been working hardly on the diversity of the size and nature of its activities and presence in the Egyptian market. Positively MENCO achieved its goal by gaining different experiences in various fields and excelled by the eagerness it showed through the years.

MENCO exerts its efforts to reach the highest standards of quality (ISO 9001:2008 ), safety and performance.

MENCO’s motto is (ON TIME COMPLETION, WITHIN BUDGET while SAFETY COMES FIRST).

 MENCO GROUP’s REFERENCE LIST is hereby presented to your goodselves knowing that this is just a sample of our operations in some famous plants and does not include all the projects executed…

For more information Kindly visit our website www.mencogroup.com

Reference List

LAFARGE HOLCIM
s NAME Date
1 Refractory Activities in L4 Jun 2018 Jun. -18
2 Refractory Activities in L2 Sept. 2018 Sep. -18
TCI SANMAR CHEMICALS S.A.E
s NAME Date
1 Mechanical commissioning & start up of PVC2 & VCM 3 June. -18
Helwan Cement Plant Reference
s NAME Date
1 Shutdown for coal mill MPS 3350BK. Sep. -18
2 RDF System installation of covering the apron feeder area Sep. -18
3 Extra work for supply and install FA and FF system for Quarry for PO#5700008872 May. -18
4 Extra work for P.O # 5700009151,Change rotor shaft Sepax # 3 May. -18
5 K2SD : quarry Activites Apr. -18
6 K2SD replace screw conv. with casing Apr. -18
7 repir by belzona R.M1 trunion March -18
8 K2SD:Mec.Activites kiln feed & kiln Area March -18
9 K2SD Feb 2018:Mec.Activites Raw mills area & RMT Feb -18
10 K2SD 2018 : quarry Activites Feb -18
11 Repair laminated box conveyor of kiln# 1 Feb -18
12 K 2 SD Feb 2018 Utility and RDF tasks Feb -18
13 K1SD:Mec.Activites Raw mills area & RMT Feb -18
14 K1SD Utility and RDF tasks Feb -18
15 K1SD:Mec.Activites kiln feed & kiln Area Feb -18
16 K#2 sheet metal cladding 300 m2 Dec. -17
17 Chains excavator installation Nov. -17
18 Civil Defense Works for Quarry Oct. -17
19 grinding C.M#7 & related equipment S/D Oct. -17
20 rehabilitate piffester pump for coal kiln August -17
21 rehabilitate bypass and E.P transportation August -17
22 K1SD-homo silos & Kiln feed activities August -17
23 revamping Packer machine 5 July -17
24 K1SD:jobs Preheater kiln I ( 2 inner pipe) July -17
25 Technical asist . Of replacement of R.M4 ( CMT)WN.KL1U , WNCC Kiln 1 upgrade Project May-17
Helwan Cement Plant Reference
S NAME Date
1 replace the trunnion of C.M#8 Apr-17
2 Supply and install the roof of the bunker Aug-16
3 install SS and ME of the AF system Dec-15
4 supply & erect main condition tower Jun-14
5 Filter Maintenance Service Contract Feb-14
6 Kiln 1 Shutdown – Preheater activities  Sep-14
7 Fabricate stainless basin Mar-13
8 Improve Safety conditions in many departments by installing auxiliary steel Structure Mar-13
platforms, stairs and handrails
9 Fabrication and Erection of two bucket elevators Line 1 & 2 Dec-13
10 Dismantling of bypass stack 100M height Dec-20 13
11 Rehabilitation air slide for kiln feed / raw mill No3, 4 Apr-2011/ Jan-2012
12 Supply inlet and outlet seal May-12
13 Repair works for homo silos Kiln feed for kiln 1 and kiln 2 Jun-12
14 erect inner pipe for two cyclones Aug-12
15 Fabricate and install Kiln inlet and outlet seals Sep-12
16 Change Gear Box of Raw Mill 3 & Make alignment Oct-12
17 Welding Service of Stiffeners on tire Oct-20 12
18 Execute Bucket Elevators Rehabilitation Jun-11
19 Repair 6 sliding gates Jun-11
20 Dismantle & install and maintain 4 dampers &crusher Aug-11
21 Replacement scooping device of Cement mill no 6 Dec-11
22 kiln 6 shutdown Jun-10
23 Technical support service for k1-SD Jun-10
24 Change the internals of symmetry gear Jun-10
25 Dismantling , machining and erecting kiln section and tire Aug -2010 /
Oct-2010/ Jan-2012
26 Supply Corrective clay Dec-09
Tourah Cement Plant Reference
s NAME Date
1 Equipment Maintenance P2 May-18
2 Equipment Maintenance P2 Apr-18
3 Equipment Maintenance P2 March-18
4 Equipment Maintenance P2 Fab-18
5 Equipment Maintenance P2 Jan-18
6 Clean 1000m2 front of nile pumps (Metaje) Jan-18
7 Equipment Maintenance P2 Dec-17
8 Change section of CM10 Nov-17
9 Equipment Maintenance P2 Nov-17
10 Equipment Maintenance P2 Oct-17
11 Tourah –Equipment Maintenance P2 Oct-17
12 Equipment Maintenance P2 Sep-17
13 Equipment Maintenance P2 Jun-17
14 Extra Work Tech. Assist.-SDK8 Fab-17
15 Mechanical Work in CM10SD Aug-16
16 Safety work for road map Nov-15
  Change the drying chamber of raw mill 9B Feb-14
17 Work in Lime Stone reclaimer Mar-14
18 General Maintenance Service Contract For Plant Mar-14
19 Install works for 1st grind. chamber RM8 Jun-14
20 Install. works of trans. diaphragm CM11 Jun-14
  Install. works of trans. diaphragm CM10 Sep-14
21 Installation of CM11 Drive unit Nov. 2014
22 Installation of Drive unit and change girth gear for CM9

 

 

May-13
23 Supply, design, fabricate, and Install Pherro Sulphet silo Jun-13
24 Utilization of CM13 for CWS project Aug-13
25 Install new platform for Raw Mill 8 and Raw mill 9 stacks @ 40 m Height Feb-12
26 Adjust & align rail way of clinker crane 3&8 Feb -2012
27 Fabricate and install Sheet metal duct work & Air outlets & exhausted Aug-12
28

 

29

Improve Safety conditions in many departments by installing auxiliary steel Structure Dec-2012-Mar
platforms, , stairs and handrails in plant 2
30 Install Air slide and pipes Sep-12
31 Change Fan for raw mill of kiln 8  
32 Install Platforms & Steel Structure for CEMs July -2011
33 Improve Safety conditions in many departments by installing auxiliary steel structure Oct-11
34 platforms, , stairs and handrails in plant 1  
35 change 2 internal roof for separators in cement mill Dec-11
36 install Gear box for separators for CEMs Dec-11
37 Sheet metal work for P1&P2 April-2011/
Oct-2011
38 Execute the shutdown for kiln 7 Feb-11
39 Change belt for bucket elevator Mar-11
40 Kiln 9 shutdown kiln feed Jun-11
41 Repair & cladding sheet metal in raw mill Sept-2011
42 Install new chimney for bypass Sept-2011
43 Repair expansion joints for kiln7 Sept-2011
44 Fabricate and install Safety cover for drag chain CM Sept-2011
45 Fabricate and install cladding sheet metal in Preheater Sep-11
46 Execute the kiln feed area shutdown activities Oct-11
47 Kiln 8 shutdown kiln feed and rotary kiln Oct-11
48 Repair water pipe line and air pipes for cement department Dec-10
49 Execute the maintenance works for kiln 5 Dec-20 10
50 Reverse symmetry for cement mill 8 Dec-10
51 Annual contract for Maintenance of 12 packing machinesin Plant 1,2 2008-to date
52 Annual contract for Maintenance of 11 Cement mills in plant 1,2 2008-to date
53 Annual contract to operate the mechanical workshop 2008-Apr2012
Titan (Beni Suef) cement Plant Reference
S Project Date
1 Change feed chute pipes and flaps Mar-14
2 Works during K1SD May 14 in Exhaust Stack Mar-14
3 Maintenance work for kiln 1 Mar-14
4 Execute the electro mechanical upgrading works for 4 Haver & Bucker rotary Jan-13
packing machines
5 repair the separators Feb-12
6 repair the bucket elevator Feb-12
7 change the waste fan’s motor, the kiln’s motor, the bypass main screw motor Feb-12
8 Repair the bypass bucket elevator Dec-12
9 erect the new dryer inside the compressor room Dec-12
10 Change the gearbox for the cooler crusher Dec-12
11 Change the membrane for the cooler Hydraulic system Dec-12
12 Change the casing of the new screw conveyor Dec-20 12
13 Change fixed & free bearing for the cooler fans Dec-12
14 Change canvas for air slides Dec-12
Reference list miscellaneous
s project Company Date
1 Menco Labor for mobile equipment depart from april to december Qattmia Cement May-18
2 labors work through shutdown from metaj Lafarge May-18
3 Change 15 m from by-pass duct Cemex Cement May-18
4 General Maintenance Qattmia Cement May-18
5 General Maintenance Qattmia Cement Apr-18
6 Install Kiln# 1new inlet seal Suez Cement March-18
7 Extra Works for Cement silo 6 Qattmia Cement Jan-18
8 Operators for LCE inter fleet Lafarge Cement March-18
9 Round axiandosa tree 2 Inch Lafarge Cement March-18
10 lafarge contract 2018 Lafarge Cement March-18
11 Equip. G.Maint. Extra(Safety Animators)L1-SD Suez Cement March-18
12 suppling material at lafarge for gardening service Lafarge Cement March-18
13 General Maintenance – MENCO Qattmia Cement Feb-18
14 change surface feeder belt Qattmia Cement Feb-18
15 Maintenance Technical Assistance Service 15 manpower Qattmia Cement Feb-18
16 General Maintenance – MENCO Qattmia Cement Jan-18
17 Urgent Requirement for Line 1 Refractory Short SD (Metaje) Suez Cement Jan-18
18 Fab,Install platforms&handrails Suez Cement Dec-17
Reference list miscellaneous
s project Company Date
19 General Maintenance – MENCO Qattmia Dec-17
20 Erection New Foundry Line Helwan Iron Foundry Dec-17
21 Katamia — Maintenance assistance Qattmia Nov-17
22 Install Kiln# 1new inlet seal Suez Cement Nov-17
23 Extra work for G.M.S.agreement -Menco Qattmia Oct-17
24 Equip. G.Maint. Support&troubleshooting Suez Cement Oct-17
25 Equip.G.Maintenane(Safety Animator)L2-SD Suez Cement Oct-17
26 Repairing ducts which done by MENCO in Raw mills area FLS @
National Cement Company
Agust-17
27 MENCO extra jobs in RM 1 & 2 FLS @
National Cement Company
Agust-17
28 Equip. G.Maint. Extra Work Line-2 SD Suez Cement Jule-17
29 Extra works done by MENCO at RM#3 FLS @
National Cement Company
Jule-17
30 New Dedusting System – Bag Filter Bolorpcchi – Suez Cement June-17
31 Repairing discharge system cement silo 6 Qattmia June-17
32 Extra works done by MENCO at RM#3 . FLS @
National Cement Company
June-17
33 extra work of kiln inlet Job -WNCC FLS@WNCC June-17
34 change the drive segments for cement be220 FLS@WNCC May-17
35 Erection New copper rolling mill equipment Helwan For Non – ferrous Industries May-17
36 Change worn fabric of the air slide .   Apr-17
Reference list miscellaneous
s project Company Date
37 WN.KL1U , WNCC Kiln 1 upgrade Project FLS SUPRVISION@
National Cement Company
Apr-17
38 WN.KL1U , WNCC Kiln 1 upgrade Project FLS SUPRVISION@
National Cement Company
Apr-17
39 WNCC OK Mill upgrade job FLS SUPRVISION@
National Cement Company
Mar-17
40 Overhaul of Ball Raw Mill 3 – NCC FLS SUPRVISION@
National Cement Company
Mar-17
41 Erect new cleaning chutes for RMs area FLS SUPRVISION@
National Cement Company
Feb-17
42 Repair the mill fan 1 impeller FLS SUPRVISION@
National Cement Company
Jan-17
43 Raw area air slides job FLS SUPRVISION@
National Cement Company
Jan-17
44 TAD repir for String 1 & 2 FLS SUPRVISION@
National Cement Company
Sep-16
45 N3.421 , Preheater Department 1 FLS SUPRVISION@
National Cement Company
Jun-16
46 Fabrication and Erection of extra quantities for crusher project FLS SUPRVISION@
National Cement Company
Mar-16
47 N3.321 , Raw Mill Department 1 FLS SUPRVISION@
National Cement Company
Nov-16
48 SEP SD Clay crusher & LS Reclaimer 2 Suez Cement Plant Dec-16
49 Strengthening of RM building line 2 Suez Cement Plant Dec-16
50 Repair damaged belt conveyor – MENCO C Suez Cement Plant Oct-16
51 Main burner L1 ST. structure support Suez Cement Plant Jul-16
52 Extra work on PO. 5700007628 Suez Cement Plant Jun-16
53 Extra work for Overhaul for Clay crusher & LS Reclaimer 2 SD 2015 Suez Cement Plant Mar-16
54 supply, fab.& install Elev. platforms Suez Cement Plant Jan-16
55 mechanical service for short KSD Katmieya plant Feb-16
56 Overtime for Menco manpower (KSD-Feb.16) Katmieya plant Feb-16
57 KILN TENDER LINE #1 AMCC@
National Cement Company
Mar-16
58 Upgrade Preheater line 3 NLS SUPRVISION@
National Cement Company
Mar-15
59  Safety Preheater Department 1 FLS SUPRVISION@
National Cement Company
Nov-15
60 fabrication/supply/erection/commissioning for the screw conveyor D630. Qty=56meters FLS SUPRVISION@
National Cement Company
Nov-15
61 fabrication/supply/erection/commissioning for the screw conveyor D630. Qty=30meters FLS SUPRVISION@
National Cement Company
Nov-15
62 fabrication/supply/erection/commissioning for the screw conveyor D630. Qty=60meters FLS SUPRVISION@
National Cement Company
Nov-15
63 we need a main contractor for NCC crusher project FLS SUPRVISION@
National Cement Company
Oct-15
64 Overhaul for rotary Kiln 1 K1 SD 2015 Suez Cement Plant Aug-15
65 Overhaul for Clay crusher & LS Reclaimer 2 and kiln Suez Cement Plant Jul-15
66 Supply & erect main condition tower Minya Plant May-14
67 Fabricate & Supply New Final Fans Casing Katmieya plant May-14
68 Supply & erect duct between Cooler and EP Filter Minya Plant May-14
69 KSD-Aug.14 Ls. Crusher & Reclaimer. MTC Katmieya plant Aug. 2014
70 Upgrade Preheater line 3 NLS SUPRVISION@
National Cement Company
Sep-14
71 started the project to execute all the mechanical installation for equipment and piping for a new polypropylene factory ; Estimated 40,000 man-hour Taghleef Industries Feb-2013- Oct2013
72 Man power supply for plant installation Quarry& Mining: Feb-Mar2013
73 Install the lining for Vertical mill separator NLS SUPRVISION: @ Arabian cement company Mar-13
74 Awarded the change of two rollers for Loesche Vertical roller mill Sinoma TCDRI @
Arish Cement company:
Apr-13
75 The main contractor HASSAN ALLAM SONS who did award apart of this project to MENCO GROUP on his own behalf. Engineering and Technical Consultant (UHDE) -All work (fabrication & erection of carbon steel & stainless piping) 90,000 inch-Erection of circular Ducts Egyptian Hydrocarbon

 

Company (EHC ) SOKHNA

Jun-13
76 accomplished the Dismantling the whole Suez Lime Plant Consisting of 6 vertical,  kilns, 1 crusher, 1 raw mill , silos and packing machines and utilities , 20,000 man hour Suez lime factory Sep-2012- Feb 2013
77 Realignment of overhead crane rails Misr beni suef Cement Feb -2012
78 Dismantling of two tanks and Engineering, Fabrication and erection of two new, cylindrical process water tanks 100 m3 each over 100 m silos Suez Cement Plant in Ain- Sokhna May -2012
79 v execute the shutdown jobs in Raw mills, v Replace air slide fabric and casing, v Repair all metallic works in preheater including ducts and expansion joints, v Replace kiln inlet seal and outlet seal for cooler excess air ducts NLSSUPERVISION: @ National Cement Company Sep-12
80 Auxiliary steel structure fabrication, erection of equipment for the New EPAB filters THERMAX Dec-11
81 Supply and installation of steel structure Kattamia cement plant Jun-09

We have various contractual agreements with leading cement companies such as:-

s NAME Date
1 Agreement of Rigger Services TPCC-2018 01/5/2018
2 Agreement of Rigger Services TPCC-2018 01/4/2018
3 Agreement of Rigger Services TPCC-2018 01/3/2018
4 Agreement of Rigger Services TPCC-2018 01/2/2018
5 Agreement of Rigger Services TPCC-2018 01/1/2018
6 Agreement of Rigger Services for tourah plant 01/11/2017
7 Agreement of Rigger Services for tourah plant 01/10/2017
8 Agreement of Rigger Services for tourah plant 01/09/2017
9 Agreement of Rigger Services for tourah plant 01/07/2017
10 services agreement for equipment maintenance for tourah plant 01/04/2014
11 services agreement for the periodic maintenance of equipments for kattamia plant 01/11/2014
12 shutdown activities service agreement for kattameya plant 01/04/2014
13 mobile equipment and trucks operation and maintenance agreement  (LAFARGE) 01/05/2016
14 services agreement of maintenance of filters for helwan plant 01/03/2014